Store Renovation II

Here's the finished ceiling/store. Well, not "finished" in the sense that the doors are opened tomorrow, more, "finished" in the sense that I'm done with all of the projects I was hired to do. There is still a plethora of things left to be accomplished, but those will be handled primarily by other people. My tasks were:
  1. Replace ceiling.
  2. Replace all door locks.
  3. Build out new window sills (those large windows on the left side of the pictures.)
  4. Build playroom walls (those half walls at the back of the store).
  5. Build out display platforms in front windows.
  6. Repair the office walls (the room on the other side of the orange wall).
  7. Replace/hang doors and hardware (4 ea).
  8. Install baseboard trim (dark green stripe all the way around the store.) 360 linear ft.
  9. Install lights in bathrooms.
  10. Repair window/door trims.
  11. Repair walls.
  12. A bunch of misc that just came up while being there.
The original completion date for all these projects to be done was 2/20/08. I started 1/5/08. On 1/12/08 I was told the painters were starting earlier than expected and I only had 10(ish) days to complete the majority of the projects (esp sense they had to paint the baseboard, walls, window sills, etc.). The last major project I did was the ceiling tiles, which I finished Thursday night/Friday morning.